Old West Main & Upper Harbor Renewal Project
Newsletter Number 31
Red Wing Riverview Skyway "Pedestrian Bridge" Update:
The pedestrian bridge is planned to remain open throughout construction of Old West Main Street this summer. The bridge will serve as a consistent means of access to Old West Main Street during construction and only expected to close during the permanent plaza construction connecting the bridge to Old West Main anticipated to be completed mid-summer.
Old West Main Street Update:
The roadway closure from the east side of Washington St. to the east side of Jefferson St. is planned for Monday, April 18. The contractor plans to start work within the intersection of Washington St., beginning with the pavement removal first thing Monday morning. Following the pavement removal, the contractor plans to focus on the new underground utilities, starting with the installation of the new sanitary sewer. All businesses along Old West Main will remain open and accessible during construction. All detour and business signing will be in place starting Monday.