[ARCHIVED] Red Wing Solid Waste Facility Reconstruction Project

Photo of in-progress light fixture installation in men's restroom at Waste Campus facility.

Red Wing Solid Waste Facility

Reconstruction Project #17206

Report Date: 12/16/2019




The reconstruction of the buildings at the Solid Waste Facility that were lost to fire in June of 2017 continues. 

During the week of December 9 through December 13. . .

  • LS Black coordinating work.
  • Parker installing electrical connections in the Mezzanine area and for door operators on the east side of the building.  Also prepping to install lights in installed ceiling grids.
  • Ryan installing and insulating water lines.
  • Pinnacle taping and mudding remaining items
  • Sylvander finalizing duct runs and installing thermostats.
  • Painters taping off doors and applying final coats in the Admin area. 
  • TCA installing ceiling grid.

A reminder to our customers and visitors – the construction zone is located in areas of the Waste Campus that have been typically accessible to customers.  Signs have been installed to provide direction.  All customers and visitors are asked to stop in the office before proceeding further into the Campus.