[ARCHIVED] Red Wing Solid Waste Facility Reconstruction Project

Detail work on the PEMB of the Waste Campus facility reconstruction.

Red Wing Solid Waste Facility

Reconstruction Project #17206

Report Date: 10/21/2019




The reconstruction of the buildings at the Solid Waste Facility that were lost to fire in June of 2017 continues. 

During the weeks of October 14 through October 18, 2019 . . .

  • LS Black caulking door frames.
  • Ironworkers continue detail work throughout and install liner panels in Maintenance-Parts and Riser Room.   
  • Bolander saw cutting pavement.
  • Pinnacle framing walls at Tip Floor and admin perimeter and installing drywall.
  • Pinnacle installing insulation at framed walls surrounding Conveyors 1 & 2.
  • Parker Electric installing electrical components throughout as needed.
  • Ryan continued installing plumbing in Maintenance-Parts, lunchroom, and hydrant.
  • Ryan began layout for air and gas piping and installing sanitary, vent, and water lines to restrooms
  • Sylvander installing connections to heating units in the Mezzanine.
  • Overhead Door began installing tracks and doors at the Loadout areas.

A reminder to our customers and visitors – the construction zone is located in areas of the Waste Campus that have been typically accessible to customers.  Signs have been installed to provide direction.  All customers and visitors are asked to stop in the office before proceeding further into the Campus.