Red Wing Solid Waste Facility
Reconstruction Project #17206
Report Date: 06/24/2019
The reconstruction of the buildings at the Solid Waste Facility that were lost to fire in June of 2017 continues.
During the week of June 17 through June 21, 2019 . . .
- Ironworkers began organizing steel for erection.
- The contractor continues forming the tipping floor walls and poured the west and north concrete walls at the tipping floor.
- Masons completed laying CMU walls.
A reminder to our customers and visitors – the construction zone is located in areas of the Solid Waste Campus that have been typically accessible to customers. Signs have been installed to provide direction. All customers and visitors are asked to stop in the office before proceeding further into the Campus.