Report Date:  4/22/19



The reconstruction of the buildings at the Solid Waste Facility that were lost to fire in June of 2017 continues. 


During the week of April 15 through April 19 . . .

  • Continued laying out and forming for the west and north concrete wall at the tipping floor

  • Began excavating to prepare for pile drilling

  • Began driving piles for the new building. 


A reminder to our customers and visitors – the construction zone is located in areas of the Solid Waste Campus that have been typically accessible to customers.  Signs have been installed to provide direction.  All customers and visitors are asked to stop in the office before proceeding further into the Campus.