2022 Street Projects

Map of 2022 Street Construction Projects in Red Wing
Map of 2022 Mill and Overlay Projects in Red Wing

2022 Residential Reconstruction (Sturtevant, Pine, and Prairia Streets)

Construction is anticipated to begin in early May with completion anticipated in late September. This schedule will be refined once the construction contract is executed and a contractor is on board .This project consists of full reconstruction including replacement of sanitary sewer, storm sewer, watermain, sewer and water services, curb and gutter, sidewalk, and bituminous pavement of the following streets:

  • Sturtevant Street (Prairia Street to West Avenue)
  • Pine Street (Putnam Avenue to Sturtevant Street)
  • Prairia Street (Putnam Avenue to Sturtevant Street)

Important dates moving to construction start: 

  • January 20, 2022 – Neighborhood Meeting to review the proposed project and answer questions from property owners and residents affected by the construction
  • February 14, 2022 – Public Hearing held during the City Council meeting prior to Council consideration to order the improvement
  • March 29, 2022 – Project bid letting date
  • April 11, 2022 – Council to consider bids and award of construction contract

2022 Red Wing Bituminous Mill & Overlay

This project will include a mill and overlay and pedestrian ramp construction in the following areas:

  • Featherstone Court (Featherstone Road to Dead End)
  • Danielson Drive (Hi Park Avenue to Cul-de-sac)
  • Old Zumbrota Street (Guernsey Lane to Beginning of Cul-de-sac)
  • West Fifth Street (Plum Street to Bluff Street)
  • West Sixth Street (Plum Street to Potter Street)
  • West Seventh Street (West Avenue to Plum Street)
  • Bush Street (West Fifth Street to West Seventh Street)
  • Bluff Street (Fourth Street to Seventh Street)
  • Centennial Street (East Fifth Street to East Seventh Street)
  • Green Street Alley

2022 Waste Campus Pavement Reclamation Project

This project includes the reclamation of all the existing bituminous pavement, regrading, and repaving all areas currently paved and adding new pavement in some gravel areas due to poor conditions. Construction is planned to begin in late summer of 2022 and to be completed in the fall of 2022.

Alley Reconstruction

Curb and gutters and bituminous paving are scheduled to begin in summer 2022 on the alley running from West Avenue starting 175 feet south of West Seventh Street intersection to the south approximately 900 feet tying back in to West Avenue.